What document is typically created to launch a project?
Answer options
- A. Bill of Materials
- B. Project Charter
- C. Work Breakdown Structure
- D. Budget
Correct answer: B
Explanation
The Project Charter is the correct answer as it formally authorizes the project and outlines its objectives, scope, and stakeholders. The Bill of Materials is related to the components required for a project, the Work Breakdown Structure is a breakdown of tasks, and the Budget pertains to the financial aspect, but none of these serve as the initiation document.