CompTIA Security+ (SY0-701) — Question 89
A company is working with a vendor to perform a penetration test. Which of the following includes an estimate about the number of hours required to complete the engagement?
Answer options
- A. SOW
- B. BPA
- C. SLA
- D. NDA
Correct answer: A
Explanation
The Statement of Work (SOW) outlines the tasks, deliverables, and estimated hours for the project, making it the correct choice. The Blanket Purchase Agreement (BPA), Service Level Agreement (SLA), and Non-Disclosure Agreement (NDA) do not typically include time estimates for specific engagements.