CompTIA Security+ (SY0-701) — Question 85

A systems administrator would like to deploy a change to a production system. Which of the following must the administrator submit to demonstrate that the system can be restored to a working state in the event of a performance issue?

Answer options

Correct answer: A

Explanation

The correct answer is A, the Backout plan, which outlines the steps to revert changes and restore the system in case of issues. Options B (Impact analysis) and C (Test procedure) focus on understanding effects and testing, while D (Approval procedure) pertains to gaining consent rather than restoration strategies.