CompTIA Security+ (SY0-701) — Question 166
Which of the following describes effective change management procedures?
Answer options
- A. Approving the change after a successful deployment
- B. Having a backout plan when a patch fails
- C. Using a spreadsheet for tracking changes
- D. Using an automatic change control bypass for security updates
Correct answer: B
Explanation
Option B is correct because having a backout plan ensures that if a patch fails, systems can be restored to their previous state, minimizing disruption. The other options are ineffective; approving changes after deployment (A) can lead to greater issues, using a spreadsheet (C) is not a systematic approach, and bypassing change control (D) can create security vulnerabilities.