CompTIA Security+ (SY0-701) — Question 12
Which of the following is required for an organization to properly manage its restore process in the event of system failure?
Answer options
- A. IRP
- B. DRP
- C. RPO
- D. SDLC
Correct answer: B
Explanation
The correct answer is B, DRP (Disaster Recovery Plan), as it outlines the procedures and resources needed to recover systems after a failure. The other options do not specifically address recovery from a disaster: A (IRP) refers to Incident Response Plan, C (RPO) relates to Recovery Point Objective, and D (SDLC) stands for Software Development Life Cycle, which is unrelated to disaster recovery.