CompTIA Security+ (SY0-601) — Question 667

An organization's corporate offices were destroyed due to a natural disaster, so the organization is now setting up offices in a temporary work space. Which of the following will the organization most likely consult?

Answer options

Correct answer: A

Explanation

The business continuity plan is designed to ensure that critical business functions can continue during and after a disaster, making it the most relevant document for setting up temporary workspaces. The risk management plan focuses on identifying and mitigating risks rather than operational continuity, while the communication plan is about informing stakeholders. The incident response plan deals with immediate responses to incidents rather than long-term operational recovery.