A technician needs to apply a high-priority patch to a production system. Which of the following steps should be taken first?
Answer options
- A. Air gap the system.
- B. Move the system to a different network segment.
- C. Create a change control request.
- D. Apply the patch to the system.
Correct answer: C
Explanation
The correct answer is C, as creating a change control request is essential for documenting and approving changes to production systems, ensuring accountability and communication. Options A and B involve network configuration changes that are not necessary before patching, while option D skips the important procedural step of obtaining approval before applying updates.