CompTIA Security+ (SY0-501) — Question 145

Six months into development, the core team assigned to implement a new internal piece of software must convene to discuss a new requirement with the stake holders. A stakeholder identified a missing feature critical to the organization, which must be implemented. The team needs to validate the feasibility of the newly introduced requirement and ensure it does not introduce new vulnerabilities to the software and other applications that will integrate with it.
Which of the following BEST describes what the company?

Answer options

Correct answer: B

Explanation

The correct answer is B because the system analysis phase is where requirements are gathered, assessed for feasibility, and analyzed for potential impacts on security. Options A, C, and D refer to different stages of the Software Development Life Cycle (SDLC) that do not focus on refining and validating new requirements, which is the primary task at this point.