CompTIA Project+ (PK0-005) — Question 98
A project manager has just finished overseeing the implementation of a new, self-service benefits enrollment system. Many employees, however, are calling the human resources team for assistance instead of using the self-service system. Which of the following should the project manager have done as part of the execution plan?
Answer options
- A. Establish a minimally viable product.
- B. Prepare new knowledge base documentation.
- C. Update the project baseline and schedule.
- D. Periodically review vendor performance.
Correct answer: B
Explanation
The correct answer is B because preparing new knowledge base documentation would provide employees with the necessary resources to understand and utilize the self-service system effectively. Options A, C, and D do not directly address the issue of employee support and system usage, as they focus on product development, project management metrics, and vendor assessment respectively.