CompTIA Project+ (PK0-005) — Question 70
A project manager reviews a new project charter and notices that the project objective is similar to a project that was done in the past. Which of the following actions should the project manager take?
Answer options
- A. Review the existing artifacts and customize accordingly.
- B. Utilize the existing artifacts to manage the project.
- C. Ask the previous project manager for advice.
- D. Notify the sponsor that this project duplicates a prior project.
Correct answer: A
Explanation
The correct answer is A because reviewing and customizing existing artifacts ensures that the project benefits from past learnings while addressing any unique aspects of the new project. Option B may not adequately address project-specific needs, C lacks proactive engagement with the existing materials, and D could be premature without further analysis of the artifacts.