CompTIA Project+ (PK0-005) — Question 50
A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?
Answer options
- A. Review the progress reports.
- B. Perform a gap analysis.
- C. Coordinate a phase-gate review.
- D. Set up touch points with the team.
Correct answer: C
Explanation
The correct answer is C, as a phase-gate review is specifically designed to evaluate the quality of work completed and ensure that necessary resources are available before moving to the next phase. Option A focuses on progress reports, which may not provide a comprehensive evaluation. Option B, a gap analysis, assesses discrepancies but doesn't necessarily confirm readiness to advance. Option D, setting up touch points, is more about ongoing communication rather than a formal assessment.