CompTIA Project+ (PK0-005) — Question 50

A segment of a project has ended. Before moving on to the next segment, the project manager wants to assess if the work produced in the previous segment meets a high enough standard and if adequate resources are available to continue the project. Which of the following should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C, as a phase-gate review is specifically designed to evaluate the quality of work completed and ensure that necessary resources are available before moving to the next phase. Option A focuses on progress reports, which may not provide a comprehensive evaluation. Option B, a gap analysis, assesses discrepancies but doesn't necessarily confirm readiness to advance. Option D, setting up touch points, is more about ongoing communication rather than a formal assessment.