CompTIA Project+ (PK0-005) — Question 373
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
Answer options
- A. A risk budget
- B. A risk impact
- C. A change request
- D. A contingency plan
Correct answer: D
Explanation
The correct answer is D, a contingency plan, as it provides predefined actions to address potential problems before they occur, thereby minimizing impact. The other options, while relevant to risk management, do not specifically focus on preparing for unforeseen issues that could disrupt operations.