CompTIA Project+ (PK0-005) — Question 361

A project manager is reviewing deliverables during the planning phase of a project. Which of the following must be completed at this stage?

Answer options

Correct answer: D

Explanation

The correct answer is D, the QA plan, as it establishes the quality standards and procedures to be followed throughout the project. While project objectives, access requirements, and the preliminary scope statement are important, they do not specifically pertain to quality assurance, which is critical to ensure that deliverables meet the required standards.