CompTIA Project+ (PK0-005) — Question 350
A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following actions should the project manager should take next?
Answer options
- A. Document the change request in the change log.
- B. Communicate the change request to stakeholders.
- C. Determine the decision makers for the change request.
- D. Validate the change request.
Correct answer: A
Explanation
The correct answer is A because documenting the change request in the change log is the first step in managing changes to the project scope. Options B, C, and D are important but they follow after the initial documentation of the request.