CompTIA Project+ (PK0-005) — Question 344
Which of the following situations would require a project manager to revise the communication plan during a project's execution?
Answer options
- A. A change is approved that impacts the project schedule and budget.
- B. The test results are not as expected.
- C. The team is unclear which meetings they should attend.
- D. A stakeholder requests some changes to the scope.
Correct answer: C
Explanation
The correct answer is C, as clarity on meeting attendance is crucial for effective communication within the team. If the team is unsure about their meeting obligations, it can lead to confusion and inefficiency. While the other options indicate issues that may impact the project, they do not directly necessitate a revision of the communication plan.