CompTIA Project+ (PK0-005) — Question 34

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Answer options

Correct answer: A

Explanation

The correct answer is A because the next logical step after testing is to validate the outcomes against the project's scope and obtain formal approval from stakeholders. Options B, C, and D are not immediate next steps; they involve ongoing quality assurance, risk management, and operational handoff, which come after validation.