CompTIA Project+ (PK0-005) — Question 34
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?
Answer options
- A. Validate against the scope statement and ask for sign-off.
- B. Run a control chart to ensure the quality of the deliverables.
- C. Review the risk register and close up residual risks.
- D. Start the training and handoff for the operations team.
Correct answer: A
Explanation
The correct answer is A because the next logical step after testing is to validate the outcomes against the project's scope and obtain formal approval from stakeholders. Options B, C, and D are not immediate next steps; they involve ongoing quality assurance, risk management, and operational handoff, which come after validation.