CompTIA Project+ (PK0-005) — Question 338
A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?
Answer options
- A. Shared folder
- B. Infrastructure
- C. Multitiered architecture
- D. Data warehouse
Correct answer: D
Explanation
The correct answer is D, Data warehouse, as it is specifically designed for storing and organizing large volumes of data from different sources. Options A (Shared folder) and B (Infrastructure) do not provide the necessary structure for data analysis, while C (Multitiered architecture) refers to a design approach rather than a specific storage solution.