CompTIA Project+ (PK0-005) — Question 312
A project came in under budget, so the senior management team celebrated by spending the unused budget on shirts for team members and a cake for the entire company. In which of the following project phases did this take place?
Answer options
- A. Planning
- B. Closing
- C. Execution
- D. Initiation
Correct answer: B
Explanation
The correct answer is B, Closing, as this phase involves finalizing all project activities and formally completing the project. The celebration of coming in under budget indicates that the project has concluded, which aligns with the Closing phase. The other options represent earlier stages of the project where such celebrations would not typically occur.