CompTIA Project+ (PK0-005) — Question 288

The development phase of a project is coming to an end, and the product is ready. The project manager needs to develop a transition/release plan to ensure a smooth launch. Which of the following activities should be included in the plan?

Answer options

Correct answer: C

Explanation

The operational handoff is essential for transferring the project's deliverables to the operations team for maintenance and support. The other options, such as preliminary needs assessment and work breakdown structure, are more relevant to earlier project phases, while budget reconciliation pertains to financial management rather than the transition process.