CompTIA Project+ (PK0-005) — Question 281
Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?
Answer options
- A. Rollback plan
- B. Downtime stage
- C. Maintenance window
- D. Validation checks
Correct answer: A
Explanation
The correct answer is A, as a rollback plan is specifically designed to revert to a previous version if issues arise. The other options do not inherently involve removing a new package; for instance, downtime stage and maintenance window refer to periods of inactivity, while validation checks are about ensuring functionality.