CompTIA Project+ (PK0-005) — Question 270
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?
Answer options
- A. Task log
- B. Cadence
- C. Milestones
- D. Work breakdown structure
Correct answer: B
Explanation
The correct answer is B, as establishing a cadence provides a predictable rhythm for the team's work, allowing for a consistent flow of tasks and deliverables. Options A, C, and D do not create a repeatable schedule; a task log tracks tasks, milestones mark key points, and a work breakdown structure organizes tasks but does not establish a rhythm.