CompTIA Project+ (PK0-005) — Question 270

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Answer options

Correct answer: B

Explanation

The correct answer is B, as establishing a cadence provides a predictable rhythm for the team's work, allowing for a consistent flow of tasks and deliverables. Options A, C, and D do not create a repeatable schedule; a task log tracks tasks, milestones mark key points, and a work breakdown structure organizes tasks but does not establish a rhythm.