CompTIA Project+ (PK0-005) — Question 27
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
Answer options
- A. Gantt chart
- B. Maintenance window schedule
- C. Functional requirements
- D. Test results
Correct answer: A
Explanation
The Gantt chart is a visual representation of the project schedule, allowing the project manager to track progress and identify delays. The other options, such as the maintenance window schedule, functional requirements, and test results, do not provide insights into overall project timelines and progress.