CompTIA Project+ (PK0-005) — Question 268
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
Answer options
- A. Project transition
- B. Project management
- C. Project communications
- D. Project quality assurance
Correct answer: D
Explanation
The team is creating a Project quality assurance plan, as it focuses on ensuring that established procedures for products are monitored and maintained. The other options do not specifically address the monitoring of procedures; Project transition deals with moving products to operational use, Project management covers the overall management of a project, and Project communications focuses on information sharing.