CompTIA Project+ (PK0-005) — Question 262
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
Answer options
- A. Key stakeholder identification
- B. Preliminary procurement
- C. Solution design determination
- D. Critical factor enlistment
Correct answer: B
Explanation
The correct answer is B, as preliminary procurement involves outlining the skills and qualifications needed for a project before formally engaging with vendors. The other options do not accurately reflect the focus on technical skills and project requirements being communicated to the vendors.