CompTIA Project+ (PK0-005) — Question 258
Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?
Answer options
- A. Update the issue log.
- B. Apply the contingency plan.
- C. Transfer the risk.
- D. Submit a change request.
Correct answer: B
Explanation
Applying the contingency plan is the correct response as it is a predefined strategy to address specific risks that have been identified. The other options, such as updating the issue log or submitting a change request, do not directly address the immediate threat posed by hackers. Transferring the risk may not be feasible in this scenario, making the contingency plan the most appropriate action.