CompTIA Project+ (PK0-005) — Question 256
While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
Answer options
- A. It highlights the performance issues of the project manager and team members.
- B. It lets the project manager know which stakeholders are allies for future projects.
- C. It helps the project manager create a more structured lessons-learned session.
- D. It identifies the stakeholders’ real opinions about the project.
Correct answer: C
Explanation
The correct answer, C, emphasizes that stakeholder feedback can enhance the structure of lessons-learned sessions, making it easier to capture valuable insights. Option A focuses on performance issues, which is not the primary goal of feedback collection. Option B is about identifying future allies, which is secondary to improving project processes. Option D is relevant but does not directly contribute to the organization of lessons learned.