CompTIA Project+ (PK0-005) — Question 245
A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?
Answer options
- A. Planning
- B. Closure
- C. Initiation
- D. Execution
Correct answer: D
Explanation
The correct answer is D, Execution, because this phase involves monitoring project performance and making necessary adjustments to stay on budget. Options A, B, and C do not pertain to actively managing expenditures, as Planning focuses on setting the budget, Closure wraps up the project, and Initiation starts the project without adjustments.