CompTIA Project+ (PK0-005) — Question 233
A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the BEST order of the stages the PM should follow to nurture the team to high performance?
Answer options
- A. Forming, storming, performing, norming, adjourning
- B. Forming, performing, storming, norming, adjourning
- C. Forming, norming, storming, performing, adjourning
- D. Forming, storming, norming, performing, adjourning
Correct answer: D
Explanation
The correct sequence is D: Forming, storming, norming, performing, adjourning. This order reflects the typical phases a team goes through, where forming and storming help address conflicts, leading to norming and ultimately performing. Options A, B, and C are incorrect as they disrupt the natural progression necessary for effective team development.