CompTIA Project+ (PK0-005) — Question 227
A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps. Which of the following actions should the project manager take?
Answer options
- A. Notify customers the downtime will take longer than expected.
- B. Add new team members to help speed up validation.
- C. Begin executing the rollback plan.
- D. Record the issue and proceed with the implementation.
Correct answer: C
Explanation
The correct action is to begin executing the rollback plan because the validation process is incomplete and has already exceeded the acceptable downtime limit. Notifying customers or adding team members may not resolve the validation issue effectively, while recording the issue and continuing might lead to further complications and extended downtime.