CompTIA Project+ (PK0-005) — Question 224
A team member identifies a critical issue in production. Which of the following should the project manager apply?
Answer options
- A. Compliance check
- B. Release plan
- C. Rollback plan
- D. Validation check
Correct answer: C
Explanation
The correct action is to apply a Rollback plan, as it allows the project manager to revert to a previous stable version of the production environment to mitigate the critical issue. The other options do not directly address the immediate need to revert changes; a Compliance check ensures adherence to standards, a Release plan outlines future deployments, and a Validation check verifies functionality but does not resolve existing problems.