CompTIA Project+ (PK0-005) — Question 217
A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
Answer options
- A. Start-to-finish
- B. Finish-to-finish
- C. Finish-to-start
- D. Start-to-start
Correct answer: C
Explanation
The correct answer is C, Finish-to-start, as it indicates that one task cannot start until another task has been completed—in this case, testing cannot begin until all requirements are finalized. The other options describe different types of dependencies that do not apply to this scenario.