CompTIA Project+ (PK0-005) — Question 199

In a functional organizational structure, a project manager is trying to avoid a project roadblock due to a mobilization fee that has not been paid to a contractor. Which of the following should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because escalating the issue to the financial controller is crucial for resolving financial matters promptly. Option A is inappropriate as authorizing payments from the contingency budget may not be within the project manager's authority. Option B, while helpful, may not resolve the issue quickly enough. Option C could lead to further complications and is not a proactive solution.