CompTIA Project+ (PK0-005) — Question 194
Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?
Answer options
- A. Risk
- B. Change
- C. Defect
- D. Issue
Correct answer: A
Explanation
The correct answer is A, as a Risk log is specifically designed to capture potential future issues that could impact the project, such as team member turnover. The other options are not appropriate; a Change log tracks modifications to the project, a Defect log records issues with the project's deliverables, and an Issue log captures current problems rather than potential risks.