CompTIA Project+ (PK0-005) — Question 194

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

Answer options

Correct answer: A

Explanation

The correct answer is A, as a Risk log is specifically designed to capture potential future issues that could impact the project, such as team member turnover. The other options are not appropriate; a Change log tracks modifications to the project, a Defect log records issues with the project's deliverables, and an Issue log captures current problems rather than potential risks.