CompTIA Project+ (PK0-005) — Question 184

A project manager is working with a new team to review a requirement for a new project. The project manager wants to create artifacts that include roles and responsibilities. Which of the following artifact types best matches these requirements?

Answer options

Correct answer: A

Explanation

The correct choice is the RACI chart, as it specifically defines roles and responsibilities within a project. The Gantt chart is used for scheduling tasks, the Burndown chart tracks progress against work completed, and the Organizational chart illustrates the structure of an organization, none of which focus on roles and responsibilities like the RACI chart does.