Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project’s timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?
Answer options
- A. Smoothing
- B. Confronting
- C. Forcing
- D. Compromising
Correct answer: D
Explanation
Compromising is the best method in this scenario as it encourages both stakeholders to find a middle ground and work towards a solution that satisfies both parties, which is essential given their past animosity. Smoothing might avoid conflict but doesn't resolve the issue, confronting could escalate tensions, and forcing may lead to resentment rather than collaboration.