CompTIA Project+ (PK0-005) — Question 166
During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?
Answer options
- A. Baseline
- B. RBS
- C. WBS
- D. Milestones
Correct answer: A
Explanation
The correct answer is A, Baseline, which is used to formalize the project's scope, schedule, and cost, ensuring all stakeholders agree on how the project will proceed. Options B (RBS) and C (WBS) are tools for resource and work breakdown, respectively, but do not serve the purpose of formalizing agreements. Option D (Milestones) represents significant points in the project timeline but does not capture the overall agreement on tasks and resources.