CompTIA Project+ (PK0-005) — Question 164
A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?
Answer options
- A. Discovery
- B. Execution
- C. Initiating
- D. Planning
Correct answer: C
Explanation
The project is in the Initiating phase when the PM is defining communication channels and access requirements, as this phase focuses on outlining the project's foundation. The other phases, such as Discovery, Execution, and Planning, involve different activities that come after the initial setup of project parameters.