CompTIA Project+ (PK0-005) — Question 162
A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?
Answer options
- A. Initiation
- B. Closing
- C. Execution
- D. Planning
Correct answer: D
Explanation
The project team is defining important aspects like the go-live date and training, which are key activities in the Planning phase. The Initiation phase is about starting the project, the Execution phase involves carrying out the project plan, and the Closing phase is focused on finalizing all project activities. Therefore, the correct answer is D, Planning.