CompTIA Project+ (PK0-005) — Question 16
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
Answer options
- A. Issue log
- B. Defect log
- C. Change log
- D. Task board
Correct answer: B
Explanation
The correct answer is B, the Defect log, as it specifically tracks bugs and issues related to software defects. The Issue log typically records general issues, the Change log documents modifications made, and the Task board is used for tracking project tasks, none of which specifically address the bug affecting data integrity.