CompTIA Project+ (PK0-005) — Question 137
During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is BEST for determining this information?
Answer options
- A. PERT chart
- B. Milestone chart
- C. Gantt chart
- D. Budget burndown chart
Correct answer: C
Explanation
A Gantt chart is the best option as it visually represents project tasks along a timeline, making it easy to identify overlaps and manage resources. A PERT chart focuses on task sequencing and dependencies but does not clearly show overlaps. A milestone chart highlights key points in a project but lacks detailed task progression. A budget burndown chart tracks expenditure over time, which is not relevant for task overlap analysis.