CompTIA Project+ (PK0-005) — Question 132
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do NEXT?
Answer options
- A. Buy a replacement for the faulty equipment.
- B. Get the maintenance team to resolve the issue.
- C. Escalate the issue to the project sponsor.
- D. Rate the severity of the impact the issue has on the project.
Correct answer: D
Explanation
The correct answer is D because understanding the severity of the issue is crucial for determining the next steps. While buying a replacement, getting maintenance help, or escalating to the sponsor may be necessary later, first assessing the impact allows for informed decision-making regarding project priorities.