CompTIA Project+ (PK0-005) — Question 13

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the next step after updating the project plan is to implement the change. Options A, B, and C are important steps in the change control process, but they should have been completed prior to the change being executed.