A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
Answer options
- A. Data plan
- B. Contingency plan
- C. Rollback plan
- D. Recovery plan
Correct answer: B
Explanation
The correct answer is B, as a contingency plan specifically addresses potential risks and outlines actions to take in case of adverse events like hurricanes. Options A, C, and D do not directly focus on risk mitigation; a data plan is for managing information, a rollback plan is for reversing changes, and a recovery plan is for restoring operations after an event.