CompTIA Project+ (PK0-005) — Question 125
A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
Answer options
- A. A project manager assigned the wrong resources.
- B. A project manager did not release the resources.
- C. A project manager did not remove the system access.
- D. A project manager did not provide the project sign-off.
Correct answer: B
Explanation
The correct answer is B because if a project manager does not release resources after their assignment, it can lead to double counting of time or effort, resulting in 200% allocation. Option A is incorrect as it refers to incorrect resource assignment, which does not directly cause over-allocation. Options C and D do not address the issue of resource allocation percentages.