CompTIA Project+ (PK0-005) — Question 125

A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Answer options

Correct answer: B

Explanation

The correct answer is B because if a project manager does not release resources after their assignment, it can lead to double counting of time or effort, resulting in 200% allocation. Option A is incorrect as it refers to incorrect resource assignment, which does not directly cause over-allocation. Options C and D do not address the issue of resource allocation percentages.