CompTIA Project+ (PK0-005) — Question 123

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

Purpose -

Scope of work -

Location of work -

Period of performance -

Deliverables schedule -

Applicable standards -

Acceptance criteria -

Special requirements -

Payment schedule -
Which of the following documents did the client provide to the project manager?

Answer options

Correct answer: D

Explanation

The document described matches the characteristics of a Statement of Work (SOW), which outlines the work required for a project. An RFP (Request for Proposal) solicits proposals from vendors, a WBS (Work Breakdown Structure) organizes project tasks, and an SLA (Service Level Agreement) defines service expectations, making them unsuitable in this context.