CompTIA Project+ (PK0-005) — Question 123
A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
Purpose -
Scope of work -
Location of work -
Period of performance -
Deliverables schedule -
Applicable standards -
Acceptance criteria -
Special requirements -
Payment schedule -
Which of the following documents did the client provide to the project manager?
Answer options
- A. RFP
- B. WBS
- C. SLA
- D. SOW
Correct answer: D
Explanation
The document described matches the characteristics of a Statement of Work (SOW), which outlines the work required for a project. An RFP (Request for Proposal) solicits proposals from vendors, a WBS (Work Breakdown Structure) organizes project tasks, and an SLA (Service Level Agreement) defines service expectations, making them unsuitable in this context.