CompTIA Project+ (PK0-005) — Question 119

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B, as having an acceptable communication channels document would outline preferred methods of communication for stakeholders, ensuring that the project manager can reach them effectively. Options A, C, and D do not specifically address communication preferences, which is crucial in this scenario.