CompTIA Project+ (PK0-005) — Question 111
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
Answer options
- A. Make an impact assessment.
- B. Prepare a new purchase order.
- C. Select a new vendor.
- D. Create a risk register.
Correct answer: A
Explanation
The first action should be to make an impact assessment to understand how the delay affects the project timeline and deliverables. Preparing a new purchase order, selecting a new vendor, or creating a risk register would be premature without first assessing the implications of the delay.