CompTIA Project+ (PK0-005) — Question 111

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Answer options

Correct answer: A

Explanation

The first action should be to make an impact assessment to understand how the delay affects the project timeline and deliverables. Preparing a new purchase order, selecting a new vendor, or creating a risk register would be premature without first assessing the implications of the delay.