CompTIA Project+ (PK0-005) — Question 107
During the course of a project, an unexpected event occurs that could ultimately benefit the company. Which of the following is the company employing if the company decides to take advantage of this opportunity?
Answer options
- A. Exploit
- B. Enhance
- C. Accept
- D. Mitigate
Correct answer: A
Explanation
The correct answer is 'Exploit', which refers to taking full advantage of a positive opportunity that presents itself. 'Enhance' involves improving an existing situation, while 'Accept' means acknowledging a risk without taking action, and 'Mitigate' refers to reducing the impact of a negative risk. None of these options align with actively leveraging a newfound opportunity.