CompTIA Project+ (PK0-005) — Question 107

During the course of a project, an unexpected event occurs that could ultimately benefit the company. Which of the following is the company employing if the company decides to take advantage of this opportunity?

Answer options

Correct answer: A

Explanation

The correct answer is 'Exploit', which refers to taking full advantage of a positive opportunity that presents itself. 'Enhance' involves improving an existing situation, while 'Accept' means acknowledging a risk without taking action, and 'Mitigate' refers to reducing the impact of a negative risk. None of these options align with actively leveraging a newfound opportunity.