CompTIA Project+ (PK0-005) — Question 105

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM MOST likely perform?

Answer options

Correct answer: D

Explanation

The correct answer is D because using existing artifacts allows the PM to leverage past experiences while adapting to the unique requirements of the current project. Options A and B focus on seeking advice or past documentation, which may not directly contribute to the immediate scope development. Option C incorrectly assumes the previous PM's expertise is sufficient to complete the project charter without considering the current project's specific context.