Which of the following BEST describes how an organization should coordinate management of multiple related projects?
Answer options
- A. Apply the SDLC process.
- B. Establish a program.
- C. Consult the CCB.
- D. Use different frameworks.
Correct answer: B
Explanation
The correct answer is B, as establishing a program allows for the coordinated management of related projects, aligning their goals and resources. Options A and D are too broad and do not specifically address the coordination aspect, while CCB in option C pertains to change management rather than project coordination.